By Bricksnwall | 2026-10-05
The NCDRC judgment said the builder will have to
pay back the total deposited sum to all the homebuyers along with 12 percent
interest within two months.
The National Consumer Disputes Redressal Commission
(NCDRC) has asked Sunworld Vandita Group to refund the money to the buyers of
its housing project in Sector 22D of Yamuna City on Yamuna Expressway, who have
been waiting for their flats for 14 years, the NCDRC said.
The builder has been directed to reimburse
the total deposited sum to all the customers with 12 per cent interest within
two months, the NCDRC’s order of August 31 said. The relevant interest will
increase to 15 per cent per annum if payment is delayed. The decision also
directs the builder to pay litigation expenses of ₹25,000 to each buyer, the
order said.
The bench of Justice AVM J. Rajendra (retd.)
and Justice Saroj Yadav rejected the builder’s contention that the delay was
due to petitions filed by farmers and litigation and said, "Once the project
was advertised and money was taken from buyers, it was the builder’s
responsibility to ensure necessary approvals and compliances.
The builder stated before the commission that
the construction work was affected due to the protest of farmers and due to the
litigation surrounding the land and due to the factors beyond the control of
the builder.
Sanjiv Gupta, promoter of the Sunworld City
project, told HT, "We have already paid the principal amount to buyers. We are
now working on paying interest as per the order of NCDRC.
The backstory
The case is of 2018 when the homebuyers
approached NCDRC, as the builder did not hand over the apartments as per the
2017 schedule.
Officials added that in 2011, the Yamuna
Expressway Industrial Development Authority (Yeida) allocated a piece of land
to Sunworld Vandita Group for the Sector-22D project. Officials noted the
builder encouraged bookings in 2012, and roughly 1,400 customers put their
money.
By 2013, customers have paid 20 to 80 percent of the flat fee, and builder-buyer agreements are signed. However, in 2017,
when some of the buyers toured the site, no construction was found, and in 2018,
they approached the NCDRC.
Out of 91 buyers who had filed a petition
against the builder, 27 eventually withdrew their names, officials added.
The case was under consideration on the
petition of a total of 64 buyers. “Officials said they had sought a full refund with
24 percent interest, ₹2 lakh compensation for mental harassment, and ₹5 lakh as
litigation costs.
Source: Hindustan Times